UC Davis Health understands construction can have an impact on nearby neighbors. To better inform residents about upcoming work outside of regular hours information will be posted to this webpage.
Please note that schedules are subject to change due to weather conditions and resource availability. The construction teams remain committed to maintaining the presented timelines to the best of their ability.
After-Hour Construction Activity
Project Name: California Tower
- Work Location: X and 45th Streets
- Work Date(s):
- March 9, 10, 12, 13, 17, 18, 20, 23, 24, 26, 27, 31
- April 1, 6, 7, 13, 14, 15, 16, 20, 21, 22, 24, 27, 29, 30
- May 1, 4, 5, 6, 7, 8, 11, 12, 13, 14, 15, 19, 20
- June 2, 3, 5, 9, 15, 17, 18, 19, 24, 29, 30
- July 1, 8, 9, 14, 20, 23, 24, 28, 30
- August 6, 10, 11, 13, 14, 21, 24, 27, 28
- September 9, 16, 18, 25
- Time Frame: Gates open at 3 a.m. and concrete pours start at 4 a.m.
- Work Being Conducted: Gravel and slab on metal deck concrete pours
- Important Project Notes: Potential dust and noise. Dust control plan, noise and lighting mitigations measures will be implemented.
- All trucks will use white sound backup alarms.
- Majority of pours will occur in the early morning during low traffic times.
- Concrete pump will remain on ground level for all pours.
- Flaggers in place to assist trucks.
- This work will:
- Prevent delays to ambulance traffic at the hospital.
- Avoid high traffic times and prevent traffic impacts from concrete and gravel trucks when many staff and patient vehicles are present.
Project Name: California Tower
- Work Location: X and 45th Streets
- Work Date(s): Weekdays, January through TBD
- Time Frame: 3 p.m. to 11 p.m.
- Work Being Conducted: Cranes and construction elevator (man-lift) will be used to conduct night stocking activities by placing materials on the Tower structure floors.
- Important Project Notes: Second shift is being conducted in the evenings to free up cranes for day construction. Noise mitigation measures will be implemented.
Weekend Construction Activity
Project Name: California Tower
- Work Location: X and 45th Streets
- Work Date(s): Saturday, September 26, 2026 and Sunday, September 27, 2026
- Time Frame: Saturday, 7 a.m. - 6 p.m. and Sunday, 9 a.m. - 6 p.m.
- Work Being Conducted:
- Saturday: Electrical rough-in for overhead and in-wall infrastructure. Plumbing rough-ins and testing on multiple floors. Duct installation. Framing in the shafts and stairwells. Delivery of aluminum extrusions for helipad, material deliveries, and general site maintenance.
- Sunday: Material deliveries and general site maintenance.
- Important Project Notes: Noise mitigation measures will be implemented.
Additional Resources