Construction Activity

UC Davis Health understands construction can have an impact on nearby neighbors. To better inform residents about upcoming work outside of regular hours information will be posted to this webpage.

Please note that schedules are subject to change due to weather conditions and resource availability. The construction teams remain committed to maintaining the presented timelines to the best of their ability.

Notice of Construction Activities: Starting on November 16, 2026, the California Tower Team will begin applying hot tar to the perimeter of the structure on Level 1. This work will continue weekdays between November 16 and January 8 (excluding Thanksgiving, Christmas, and New Year's Day) from 7:00 a.m. to 3:00 p.m. Roof tar will produce unpleasant odors outside around the structure, similar to burned rubber from car tires. This construction activity will be rescheduled if wind speeds reach or exceed 15 mph. We apologize for any inconvenience. Please contact Government and Community Relations at community.relations@health.ucdavis.edu with any questions. 

After-Hour Construction Activity 

Project Name: California Tower

  • Work Location: X and 45th Streets
  • Work Date(s): 
    • March 9, 10, 12, 13, 17, 18, 20, 23, 24, 26, 27, 31
    • April 1, 6, 7, 13, 14, 15, 16, 20, 21, 22, 24, 27, 29, 30
    • May 1, 4, 5, 6, 7, 8, 11, 12, 13, 14, 15, 19, 20 
    • June 2, 3, 5, 9, 15, 17, 18, 19, 24, 29, 30
    • July 1, 8, 9, 14, 20, 23, 24, 28, 30
    • August 6, 10, 11, 13, 14, 21, 24, 27, 28
    • September 9, 16, 18, 25
    • October 2
  • Time Frame: Gates open at 3 a.m. and concrete pours start at 4 a.m.
  • Work Being Conducted: Gravel and slab on metal deck concrete pours
  • Important Project Notes: Potential dust and noise. Dust control plan, noise and lighting mitigations measures will be implemented.
    • All trucks will use white sound backup alarms.
    • Majority of pours will occur in the early morning during low traffic times.
    • Concrete pump will remain on ground level for all pours.
    • Flaggers in place to assist trucks.
  • This work will:
    • Prevent delays to ambulance traffic at the hospital. 
    • Avoid high traffic times and prevent traffic impacts from concrete and gravel trucks when many staff and patient vehicles are present. 

Project Name: California Tower

  • Work Location: X and 45th Streets
  • Work Date(s): Weekdays, January through TBD
  • Time Frame: 3 p.m. to 11 p.m.
  • Work Being Conducted: Cranes and construction elevator (man-lift) will be used to conduct night stocking activities by placing materials on the Tower structure floors. 
  • Important Project Notes: Second shift is being conducted in the evenings to free up cranes for day construction. Noise mitigation measures will be implemented.

Weekend Construction Activity

Project Name: California Tower

Please note the California Tower project site will be closed on Thursday, November 26 and Friday, November 27. The site will re-open for weekend work during approved EIR working hours, see below for details.

  • Work Location: X and 45th Streets
  • Work Date(s): Saturday, November 28, 2026 and Sunday, November 29, 2026 
  • Time Frame: Saturday, 7 a.m. - 6 p.m. and Sunday, 9 a.m. - 6 p.m.
  • Work Being Conducted: 
    • Saturday: Installation of framing in elevator shafts throughout tower. Rough-in on multiple levels of tower. Temporary heating system installation. Pressure testing on multiple levels. In-wall and overhead installation of acoustical insulation. Material deliveries and general site maintenance. 
    • Sunday: Framing in elevator shafts in tower. Site safety oversight, material deliveries, and general site maintenance. 
  • Important Project Notes: Noise mitigation measures will be implemented. 