Construction activity: Central Utility Plant Make Ready Phase
The Central Utility Plant (CUP) Make Ready Phase will begin Tuesday, Jan. 21, and is estimated to be complete in June 2027.
Please note the following details of this activity:
• Impacted areas include the Facilities Support Service Building (FSSB) and surrounding area, the PS6 Driveway and Parking Lot 20 (see below).
• The Make Ready Phase will consist of site groundwork, clearing and grub of surrounding areas as needed and utility relocation in preparation for the existing CUP improvements, and the relocation of the PS6 driveway.
• The new location of the PS6 driveway will be between Aggie Square and FSSB from PS6 to Second Ave and include a signalized intersection at Second Ave.
• The FSSB open space adjacent to the Gross Anatomy Lab and the Gross Anatomy Lab will be cleared and demoed in preparation for the new driveway.
• New accessible walk paths will be provided from PS6 to Second Ave and PS6 to FSSB, and existing walk paths will be protected and maintained.
• Upon completion of the new PS6 driveway, the new CUP Annex Building will be constructed over the existing PS6 driveway.
• Traffic control will be in place during installation to minimize impacts on traffic flow and parking.
For further assistance, please contact Jake Bertacchi at j.bertacchi@ccm.to or Wes Ramirez at wesramirez@ucdavis.edu.