Construction activity: Temporary SESP third-floor OR shutdowns

(SACRAMENTO)

On August 22, 23 and 29, Swinerton/Steris will shut down ORs 36, 37 and 38, respectively, to install monitors.

The work will include containment setup, wall repair, bracket installation, monitor mounting, cabling, USB extender installation and system testing. EVS terminal cleaning will be required at the end of each day.

Graphic of OR closure details.
Impacted areas.

Please note the following details of the activity:

OR36 – Saturday, August 22

  • 3 to 6 a.m. – Construction Team: Set up containment in OR36.

  • 6 to 8 p.m. – Construction Work: Remove poster, repair and paint wall, install second OR monitor bracket. Steris installation and testing of devices.

  • 8 to 9 p.m. – EVS: Terminal clean OR 36.

OR37 – Sunday, August 23

  • 3 to 6 a.m. – Construction Team: Set up containment in OR37.

  • 6 to 8 p.m. – Construction Work: Remove poster, repair and paint wall, install second OR monitor bracket. Steris installation and testing of devices.

  • 8 to 9 p.m. – EVS: Terminal clean OR 37.

OR38 – Saturday, August 29

  • 3 to 6 a.m. – Construction Team: Set up containment in OR38.

  • 6 to 8 p.m. – Construction Work: Remove poster, repair and paint wall, install second OR monitor bracket. Steris installation and testing of devices.

  • 8 to 9 p.m. – EVS: Terminal clean OR 38.