December photo update: Peek behind the California Tower fence

(SACRAMENTO)

Although the weather conditions have been less than ideal lately, the California Tower construction team expects to complete the last section of the concrete slab before year-end. The remaining soil from the mass excavation is being removed from the site in preparation for pouring the last section. At the same time, the team is working on the grading and soil compaction.

The crane pad is receiving rebar, and the work on the temporary power, north, and south connectors, as well as the underpinning underneath stair G, is progressing as expected. The dewatering system fully functions and removes all water accumulation from the site pit from the rain. 

The California Tower project will include a 14-story hospital tower and a 5-story pavilion that will deliver superior care for Northern Californians and adapt to meet the community's evolving needs.

December 2024

November 2024

October 2024

August 2024

 

Photos courtesy: Nicolas Felix Soares de Sousa, Cambridge CM, Inc., and Wayne Tilcock, photographer, UC Davis Health