November California Tower Update: Peek behind the construction fence

(SACRAMENTO)

The California Tower at UC Davis Health is rapidly taking shape from concept to reality, with its impressive structure visible along Highway 50.

Slated for completion in 2030, this transformative project will bring a 14-story hospital tower and a 5-story pavilion to life—expanding access to world-class care and meeting the evolving needs of Northern California communities. Designed with cutting-edge technology and patient-centered spaces, the tower will elevate the care experience while advancing medical research. Beyond increasing capacity, the project will generate hundreds of jobs and strengthen health equity for underserved populations. This bold investment underscores UC Davis Health’s commitment to innovation and improving health outcomes for generations to come.

Progress in November

  • South Side: Steel erection for Sequence 24 (Level 14) is 80% complete.
  • North Side: Steel erection for Sequence 25 (Level 15) is 75% complete.
  • Slab on Metal Deck:
    • Level 2: Complete
    • Level 3: 90% complete
    • Level 4: 20% complete
    • Slab on Grade (Basement): 70% complete.
    • Level 1 Cast-In-Place Deck: Formwork is 25% complete (Pour 1 formwork complete, not the pour itself).
  • Interiors: Rough-ins and finishes have started; framing mockups and fireproofing are in progress.

What’s Coming in December

  • South Side: Sequence 26 (Level 15) erection will be complete – TOPPING OUT!
  • North Side: Sequence 25 (Level 15) erection will be complete – TOPPING OUT!
  • Slab on Metal Deck:
    • Levels 2–3: Complete
    • Level 4: 95% complete
    • Level 5: 60% complete
    • Slab on Grade (Basement): Will be fully complete by end of December.
    • Level 1 Cast-In-Place Deck: Formwork will reach 90% completion.
  • Interiors: Updates will follow once construction rhythm is established.

Key Highlights

  • Steel Erection Topping Out: Mid-December milestone!
  • Weather Impact: Slight delay due to bad weather, but no major schedule impact.
  • Basement Slab: Full completion expected by end of December.

November 2025

October 2025

September 2025

August 2025

July 2025

June 2025

May 2025

April 2025

March 2025

February 2025

January 2025

December 2024

November 2024

October 2024

August 2024

 

Photos courtesy: Nicolas Felix Soares de Sousa, Cambridge CM, Inc., and Wayne Tilcock, photographer, UC Davis Health